Houston Airports has a five-year capital improvement program (CIP), approved by the City of Houston City Council, which calls for $2.05 billion of spending through fiscal year 2022. The capital improvements are concentrated in terminal and airfield projects with the majority dedicated to George Bush Intercontinental Airport. An updated CIP is approved annually by the Houston City Council as part of each new fiscal year. This CIP was approved on June 28, 2017 by City Council.
Click here to download the latest Houston Airports 5-Year CIP summary.
Project No | Location | Phase | Project Description | Estimated Date | Estimated Budget (000) |
546 | IAH | DB | UPGRADE & RELOCATE APM FACILITIES | 8/1/2019 | 29,000 |
618A |
IAH |
C |
TUNNEL DRAINAGE IMPROVEMENTS (WATER ISSUES) |
10/1/2019 |
2,250 |
646A |
IAH |
C |
RECONSTRUCT TAXIWAYS RA, SA & SB |
7/1/2020 |
66,950 |
646D | IAH | C | AMS - TAXIWAY RB EAST PANNEL REHAB - PRIORITY - IAH | 7/1/2020 | 2,794 |
668 |
IAH |
C |
REHABILITATE & EXPAND ARFF STATION 92 |
1/1/2020 |
10,403 |
669 | HOU | C | REHABILITATE & EXPAND ARFF STATION 81 | 6/1/2021 | 1,857 |
672 | HOU | C | HOBBY DRAINAGE - ROADWAY FLOODING | 6/1/2019 | 3,245 |
673 |
IAH |
DB |
TERMINAL A MODERNIZATION PROGRAM |
12/1/2019 |
196,761 |
673 | IAH | C | TERM A MODERN - ADDITIONAL RESTROOMS & TERM CURBSIDE | 12/1/2020 | 18,000 |
673B | IAH | C | DOMESTIC EXPANSION - TICKET COUNTERS, FF&E, BAGGAGE SYS | 6/1/2020 |
15,000 |
673B | IAH | C | DOMESTIC EXPANSION - CONTRUCTION (GATES + PAVEMENT) | 6/1/2021 | 310,000 |
686 |
IAH |
C |
IAH STORM WATER POLLUTION CONTROL SYS - ENVIRON LIFT ST |
12/1/2019 |
5,204 |
735A | IAH | C | IAH EXIT LANE TECHNOLOGY - MULTI-YEAR | 12/1/2019 | 5,580 |
735B |
HOU | C | HOU EXIT LANE TECHNOLOGY - MULTI-YEAR | 8/1/2020 | 1,530 |
740 |
IAH |
C |
IAH FLEET MAINTENANCE BUILDING |
9/1/2019 |
15,586 |
749 |
IAH |
C |
TERMINAL A & B PAVER REMOVAL AT IAH |
9/1/2019 |
2,472 |
762 |
IAH |
C |
INTERNAL SIGNAGE - TERMINAL B NORTH/TERMINAL C SOUTH |
7/1/2019 |
3,045 |
768TD |
IAH |
O |
COMMON USE TICKET & GATE CHECK-IN COMPUTER SYS - TERM D |
7/1/2019 |
1,277 |
770 | HOU | C | HOU - NON-STANDARD FAA TAXIWAYS | 12/1/2019 | 13,390 |
781 | HAS | O | ON CALL TECHNOLOGY CONTRACTS | 9/1/2019 | 4,500 |
783A | IAH | O | PARKING REVENUE CONTROL SYSTEM AT GBIAH | 9/1/2019 | 7,859 |
783B | HOU | O | PARKING REVENUE CONTROL SYSTEM AT HOU | 9/1/2019 | 5,501 |
784 | HAS | C | PUBLIC WI-FI EXPANSION INTO CONCESSION AREAS | 9/1/2019 | 3,296 |
793 | HAS | C | DATA CENTER-NETWORK & CLOUD REDUNDANCY | 9/1/2019 | 3,193 |
794 | HAS | C | WAYFINDING GARAGE FACILITIES AT IAH/HOU | 9/1/2019 | 1,900 |
822 | IAH | DB | ENABLING UTILITIES - LANDSIDE | 11/1/2020 | 37,691 |
826 | IAH | C | MLIT - TERMINAL, AIRSIDE, LANDSIDE | 7/1/2020 | 184,183 |
828 |
IAH |
C |
FIS CAPACITY EXPANSION |
8/1/2020 |
170,843 |
835 |
IAH |
C |
ROADWAY REHABILITATION |
1/1/2020 |
5,000 |
835 |
IAH |
C |
ROADWAY REHABILITATION |
1/1/2021 |
37,515 |
901 |
IAH |
C |
TAXIWAY WB RECONSTRUCTION | 6/1/2020 | 54,854 |
908 | HAS | O | IDENTITY MANAGEMENT SYSTEM (IDMS) | 8/1/2019 | 2,000 |
914 | IAH | C | TERMINAL C GARAGE ADDITIONAL PARKING DECKS | 7/1/2020 | 18,000 |
915 | IAH | C | REHAB TERMINAL B CONTRACT GARAGE | 7/1/2020 | 5,333 |
917 | HOU | C | HOBBY CONSOLIDATED MAINTENANCE COMPLEX | 10/1/2020 | 8,550 |
919 | HOU | O | REPLACE CARPET WITH TERRAZZO TILE IN CENTRAL CONCOURSE | 7/1/2019 | 1,717 |
922 | IAH | C | ARFF AQUEOUS FIRE FIGHTING FOAM COLLECTION FACILITY | 8/1/2020 | 7,560 |